The transportation systems generally constitute the largest public-sector investment by any society. Despite of funding limitations, highway agencies continue striving to develop road network to meet needs of the society. In order to ensure optimal utilization of public money, there is a dire need of best project evaluation practices and monitoring of the expected impacts of highway investment decisions. Present study focused on post implementation evaluation of Lahore-Sheikhupura-Faisalabad Dual Carriageway, a 4-lane divided highway 115 Kilometer long that was constructed in 2006 through Build-Operate-Transfer (BOT) financing with a concession period of 22 years. For post-implementation evaluation five performance criteria were considered: safety, vehicle operating cost, fuel cost, lifecycle agency maintenance and operations cost, and lifecycle toll collection. Post-implementation evaluation was carried out using highway maintenance and rehabilitation strategies proposed by facility operator (concessioner). Present worth (2007 constant US$) of travel time, safety and fuel saving was found to be $US 429.290, -1.790, 65.080 Million respectively. Using facility operator’s maintenance and rehabilitation strategy total maintenance and operations cost was found to be $US 234.442 Million (2007 constant US$). Also, present worth of toll collection was estimated as $US 131.410 Million (2007 constant US$). Positive net present value revealed that project is economically viable for society. Also, methodology used in present study can be used by highway agencies for carrying out post-construction evaluation of their projects.
Published in | International Journal of Transportation Engineering and Technology (Volume 4, Issue 3) |
DOI | 10.11648/j.ijtet.20180403.12 |
Page(s) | 59-64 |
Creative Commons |
This is an Open Access article, distributed under the terms of the Creative Commons Attribution 4.0 International License (http://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution and reproduction in any medium or format, provided the original work is properly cited. |
Copyright |
Copyright © The Author(s), 2019. Published by Science Publishing Group |
Post-Implementation Evaluation, BOT Project, Pakistan, Economic Efficiency
[1] | Khan M. A., Ahmed, A, Kayani W. (2018). Optimal Timing for Lane (s) Addition to an Existing Highway: A Benefit-Cost Approach. Arab J Sci Eng (2018). https://doi.org/10.1007/s13369-018-3350-8. |
[2] | Sinha, K. C. & Labi, S. (2007). Transportation decision making: Principles of project evaluation and programming, John Wiley & Sons. |
[3] | New Zealand Transport Agency (2014). Post Implementation Review Lake Road Widening. Available at https://www.nzta.govt.nz/assets/planning-and-investment/docs /post-implementation-reviews/2013-2014-pir-auckland-transp ort-lake-road-widening.pdf. |
[4] | Cambridge Systematics. (2000). A Guidebook for Performance- Based Transportation Planning, NCHRP Rep. 446, National Academy Press, Washington, DC. |
[5] | TRB (2000). Highway Capacity Manual, Transportation Research Board, National Research Council, Washington, DC. |
[6] | COMSIS Corporation, Scientific Applications International Corporation, Garman Associates (1995). Development of Diurnal Traffic Distribution and Daily, Peak, and Off-Peak Vehicle Speed Estimation Procedures for Air Quality Planning, Work Order B-94-06, Federal Highway Administration, U.S. Department of Transportation, Washington, DC. |
[7] | FHWA (1998). Highway Statistics, 1997. Office of Highway Information Management, Federal Highway Administration, Washington, DC. |
[8] | Bai Q., Ahmed A., Labi S Sinha KC (2017). Traffic Volume Benchmarks for Major Arterial Widening versus Expressway Construction: Exploratory Approach. Journal of Transportation Engineering, Part A: Systems, 2017, 143 (8). |
[9] | AASHTO (2003). User Benefit Analysis for Highways, American Association of State Highway and Transportation Officials, Washington, DC. |
[10] | Diaz, C. E. D. “A Framework for Determining the Viability of Public-Private Partnerships for Toll Road Projects in the Philippines”. Journal of the Eastern Asia Society for Transportation Studies, vol. 8, pp. 174-186, 2010. |
[11] | Azmi Mohamed et al. A Framework and Evaluation Technique for Project’s Viability of Privatization Highway Projects in Malaysia. International Journal of Engineering and Technology Vol 9 No 6 Dec 2017. |
[12] | NSC (2001). “Estimating the Costs of unintentional Injuries”. 2000 National Safety Council, Spring Lake Drive, Itasca, IL. |
[13] | Lahore and Faisalabad Construction Company (LAFCO) Private Limited (2005). Concession Agreement LAFCO. |
[14] | Kahyaogullari, B. (2013). Public-private partnerships in developing and developed countries: the UK and Turkish cases, Afyon Kocatepe Üniversitesi, IIBF Dergisi C. XV, S. II, 2013. |
[15] | Durdyev, Serdar & Ismail, Syuhaida. (2017). The build-operate-transfer model as an infrastructure privatization strategy for Turkmenistan. Utilities Policy. 48. 195-200. 10.1016/j.jup.2016.12.002. |
[16] | Sharaffudin, H., Al-Mutairi, A., (2015). Success factors for the implementation of the build operate transfer (BOT) projects in Kuwait. Int. J. Bus. Manag. 10 (9), 68e78. |
[17] | Alinaitwe, H. and Ayesiga, R. (2013). ‘Success Factors for the Implementation of Public Private Partnerships in the Construction Industry in Uganda’, Journal of Construction in Developing Countries, 18 (2), 1-14. |
[18] | Ahmadabadi A. A., Heravi G. (2018). The effect of critical success factors on project success in Public-Private Partnership projects: A case study of highway projects in Iran, Transport Policy, 2018. https://doi.org/10.1016/j.tranpol.2018.07.004. |
APA Style
Anwaar Ahmed, Sandeerah Choudhary, Muhammad Irfan. (2019). Post Implementation Evaluation of Lahore - Sheikhupura - Faisalabad Dual Carriageway - A Built Operate Transfer (BOT) Project. International Journal of Transportation Engineering and Technology, 4(3), 59-64. https://doi.org/10.11648/j.ijtet.20180403.12
ACS Style
Anwaar Ahmed; Sandeerah Choudhary; Muhammad Irfan. Post Implementation Evaluation of Lahore - Sheikhupura - Faisalabad Dual Carriageway - A Built Operate Transfer (BOT) Project. Int. J. Transp. Eng. Technol. 2019, 4(3), 59-64. doi: 10.11648/j.ijtet.20180403.12
AMA Style
Anwaar Ahmed, Sandeerah Choudhary, Muhammad Irfan. Post Implementation Evaluation of Lahore - Sheikhupura - Faisalabad Dual Carriageway - A Built Operate Transfer (BOT) Project. Int J Transp Eng Technol. 2019;4(3):59-64. doi: 10.11648/j.ijtet.20180403.12
@article{10.11648/j.ijtet.20180403.12, author = {Anwaar Ahmed and Sandeerah Choudhary and Muhammad Irfan}, title = {Post Implementation Evaluation of Lahore - Sheikhupura - Faisalabad Dual Carriageway - A Built Operate Transfer (BOT) Project}, journal = {International Journal of Transportation Engineering and Technology}, volume = {4}, number = {3}, pages = {59-64}, doi = {10.11648/j.ijtet.20180403.12}, url = {https://doi.org/10.11648/j.ijtet.20180403.12}, eprint = {https://article.sciencepublishinggroup.com/pdf/10.11648.j.ijtet.20180403.12}, abstract = {The transportation systems generally constitute the largest public-sector investment by any society. Despite of funding limitations, highway agencies continue striving to develop road network to meet needs of the society. In order to ensure optimal utilization of public money, there is a dire need of best project evaluation practices and monitoring of the expected impacts of highway investment decisions. Present study focused on post implementation evaluation of Lahore-Sheikhupura-Faisalabad Dual Carriageway, a 4-lane divided highway 115 Kilometer long that was constructed in 2006 through Build-Operate-Transfer (BOT) financing with a concession period of 22 years. For post-implementation evaluation five performance criteria were considered: safety, vehicle operating cost, fuel cost, lifecycle agency maintenance and operations cost, and lifecycle toll collection. Post-implementation evaluation was carried out using highway maintenance and rehabilitation strategies proposed by facility operator (concessioner). Present worth (2007 constant US$) of travel time, safety and fuel saving was found to be $US 429.290, -1.790, 65.080 Million respectively. Using facility operator’s maintenance and rehabilitation strategy total maintenance and operations cost was found to be $US 234.442 Million (2007 constant US$). Also, present worth of toll collection was estimated as $US 131.410 Million (2007 constant US$). Positive net present value revealed that project is economically viable for society. Also, methodology used in present study can be used by highway agencies for carrying out post-construction evaluation of their projects.}, year = {2019} }
TY - JOUR T1 - Post Implementation Evaluation of Lahore - Sheikhupura - Faisalabad Dual Carriageway - A Built Operate Transfer (BOT) Project AU - Anwaar Ahmed AU - Sandeerah Choudhary AU - Muhammad Irfan Y1 - 2019/01/05 PY - 2019 N1 - https://doi.org/10.11648/j.ijtet.20180403.12 DO - 10.11648/j.ijtet.20180403.12 T2 - International Journal of Transportation Engineering and Technology JF - International Journal of Transportation Engineering and Technology JO - International Journal of Transportation Engineering and Technology SP - 59 EP - 64 PB - Science Publishing Group SN - 2575-1751 UR - https://doi.org/10.11648/j.ijtet.20180403.12 AB - The transportation systems generally constitute the largest public-sector investment by any society. Despite of funding limitations, highway agencies continue striving to develop road network to meet needs of the society. In order to ensure optimal utilization of public money, there is a dire need of best project evaluation practices and monitoring of the expected impacts of highway investment decisions. Present study focused on post implementation evaluation of Lahore-Sheikhupura-Faisalabad Dual Carriageway, a 4-lane divided highway 115 Kilometer long that was constructed in 2006 through Build-Operate-Transfer (BOT) financing with a concession period of 22 years. For post-implementation evaluation five performance criteria were considered: safety, vehicle operating cost, fuel cost, lifecycle agency maintenance and operations cost, and lifecycle toll collection. Post-implementation evaluation was carried out using highway maintenance and rehabilitation strategies proposed by facility operator (concessioner). Present worth (2007 constant US$) of travel time, safety and fuel saving was found to be $US 429.290, -1.790, 65.080 Million respectively. Using facility operator’s maintenance and rehabilitation strategy total maintenance and operations cost was found to be $US 234.442 Million (2007 constant US$). Also, present worth of toll collection was estimated as $US 131.410 Million (2007 constant US$). Positive net present value revealed that project is economically viable for society. Also, methodology used in present study can be used by highway agencies for carrying out post-construction evaluation of their projects. VL - 4 IS - 3 ER -